Pipeline Rd. Emergency Slope Stabilization
Coquitlam, British Columbia
Project Description
SweetTech was retained by Lehigh Hanson Materials Ltd. to help manage an emergency slope stabilization project following failure of an active mine bench. SweetTech has been involved as the project manage, leading a response to this emergency repair. Work involved to date has included, hydrological analysis and drainage design, mine and operations planning, construction support, procurement and organization of external contractors, slope stability assessments, geotechnical drilling, installation of slope monitoring equipment, drafting support and 3D modelling, and on-site construction support.
Key Elements
Client
Lehigh Hanson Materials Ltd.
Timeline
November 2018 – Ongoing
Capital Cost
$1.5 Million
Engineering Services
- Construction Monitoring & Support
- Geotechnical Engineering
- Project Management
- Hydraulic and Hydrological Analysis
- Mine and Operations Planning
- Construction Execution Plans
- Slope Stability Assessment
- Geotechnical Drilling
- Drafting Support and 3D Modelling
- Procurement & Contractor Support